Digues du Rhône du Symadrem : retour d’expérience de quatre chantiers réalisés entre 1998 et 2018 et évolution de la conception et du cahier des charges des terrassements
Symadrem Rhone Levees: feedback from four sites completed between 1998 and 2018 and changes in earthworks design and specifications
1
SYMADREM,
Arles, France
2
SUEZ Environnement,
Aix-en-Provence, France
3
EGISeau,
Montpellier, France
4
ISL Ingénierie,
Montpellier, France
5
GUINTOLI,
Arles, France
6
VALERIAN,
Courthezon, France
7
MASONI TP,
Arles, France
★ Auteur de correspondance : thibaut.mallet@symadrem.fr
Le Symadrem est responsable d’un parc de 210 km de digues fluviales et 25 km de digues maritimes dans le delta du Rhône. Créé après les inondations de 1993 et 1994 en lieu et place d’associations syndicales de riverains, il s’efforce, depuis sa création, de remettre à niveau vis-à-vis de l’état de l’art ses ouvrages de protection. Le présent article présente le retour d’expérience de quatre chantiers réalisés entre 1998 et 2018. Il dresse un bilan de l’évolution de la conception des ouvrages et du cahier des charges au prisme des prescriptions de mise en œuvre des remblais étanches, des objectifs de compacité et de teneur en eau des matériaux avant compactage. Il évoque également la fréquence des contrôles prescrits et effectivement réalisés et conclut sur l’évolution dans les cahiers de charges de l’atteinte d’un objectif de résultats à l’atteinte désormais d’objectifs de résultats et de moyens matériels à employer.
Abstract
Symadrem is responsible of management of 210 km of river levees and 25 km of sea levees in the Rhone delta. Created after the floods of 1993 and 1994 in place of associations of local residents, since its creation, it has been trying to “bring back to the state of the art” its protective works. This article presents the experience gained from four projects carried out between 1998 and 2018. It reviews the evolution of the design of the structures and the specifications in the context of compaction requirements, compactness objectives and water content of the materials before compaction. He also mentions the frequency of the controls prescribed and actually carried out and concludes on the evolution in the specifications from the achievement of objectives of results to the achievement of objectives of results and material means to use.
Mots clés : digues / terrassement / teneur en eau construction / retour d’expérience / contrôle / compactage / filtration
Key words: levee / earthwork / moisture content / background / control / compaction / filtration
© CFMS-CFGI-CFMR-CFG, 2020
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.